North End Braes Stabilisation Project Completed

Posted by CBAG on August 11, 2019

CBAG are very pleased to report that the North End braes stabilisation project has now been successfully completed. The project involved the deployment of a Platipus ground anchoring solution below North End.

The project saw its initial funding awarded two years ago. Due to the size of the area, the intent was always to execute the works in two phases, during 2018 and 2019. Although challenges along the way forced us to adjust our execution plan, we managed to deliver this project on time and on budget!

CBAG would like to thank everybody involved in delivering this project, and the St. John’s Hill Wind Farm Community Fund and the Hillhead of Auquhirie Wind Farm Community Fund for funding this project.

Please also have a look at the various photographs in our gallery.

Tags: 2019 Braes Platipus St Johns Hill Wind Farm Community Fund Hillhead of Auquhirie Wind Farm Community Fund